It's been a busy time lately. I have got the internal pipework complete now.
Connected mains to new tank.
Connected pipework going to 3 toilets and 1 washing machine.
I have had some help from a Friend getting the pipework in as needed to do some pipe bending and soldering. He has done a great job. It took a little long than expected as I had to remove a toilet in the en-suite to get better access. I have to now test for leaks.
Got the ball valve modified so that it sits at the bottom of the tank.
Will follow up with some more pics later this week.
What I have got left:
I have got to connect up the overflow on the tank and leak test the cooper pipe work.
Connect up the plastic pipe work to the loft tank.
Connect up the electrics to the pump.
We have also just got a price rise in the water also. So should have this working in time before we start paying the new price.